SAP C_TSCM42_67 Exam Description:

The certification "SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7" verifies the knowledge in the area of Production for the consultant profile. This certificate proves that the candidate has a basic understanding within this consultant profile and can implement this knowledge practically in projects. The SAP Certified Application Associate can contribute to the success of the planning and implementation phases of the project in a mentored role and would typically have a maximum of three years experience in the solution area. Project experience should not be prerequisite for a competent and well trained candidate to pass this exam.


SAP PP Certification Exam Details:

Passing ScoreC_TSCM42_67 - 63%
Exam Price$550 (USD)
Reference BooksSCM240,SCM310, SCM300, SCM130, PLM114, TERP50, TERP01,SCM365
Schedule ExamSAP Training
Duration180 mins
Number of Questions80
Exam NameSAP Certified Application Associate – Production Planning & Manufacturing with SAP ERP 6.0 EHP7
LevelAssociate
Exam CodeC_TSCM42_67
Sample QuestionsSAP PP Certification Sample Questions


SAP C_TSCM42_67 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Production Orders Advanced (PP-SFC)
Topic 2
  • Material Requirements Planning (PP-MRP)
Topic 3
  • Application Overview and Backgro
Topic 4
  • Production Orders Basics (PP-SFC)
Topic 5
  • Material and Capacity Requirements Planning
Topic 6
  • Lean Manufacturing (PP-REM| PP-KAB)
Topic 7
  • Master Data (LDM)

 

NEW QUESTION 28
The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?

  • A. Activate the freely usable stock in the scope of check.
  • B. Differentiated assignment of two different checking rules in check control.
  • C. Enter an appropriate availability checking rule in the order type.
  • D. Enter an appropriate availability checking group in the material master.

Answer: B

 

NEW QUESTION 29
Which of the following structural elements does a process order have? (Choose three.)

  • A. Parallel sequences
  • B. Characteristic-based process instructions
  • C. Phases
  • D. Item data
  • E. Relationships

Answer: B,C,E

 

NEW QUESTION 30
Which activity can trigger an automatic availability check for the components of a production order?

  • A. Material staging
  • B. Goods receipt for a missing part
  • C. Order release
  • D. Order rescheduling

Answer: C

 

NEW QUESTION 31
In which master data object do you set the standard values for an operation?

  • A. Material Master
  • B. Production Resource/Tool (PRT)
  • C. Routing
  • D. Work Center

Answer: C

 

NEW QUESTION 32
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)

  • A. Production Scheduling Profile
  • B. Material Master (Finished Product)
  • C. Routing
  • D. Material Master (Component)
  • E. Work Center

Answer: C,D,E

 

NEW QUESTION 33
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)

  • A. General values from work scheduling view in the material master
  • B. User-defined field from operation in task list
  • C. General operation values in task list
  • D. General item values in bill of materials
  • E. Standard value from operation in task list

Answer: B,C,E

 

NEW QUESTION 34
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order.
The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
What do you have to consider for the two lists at this stage? (Choose two)

  • A. The MRP list displays the production order.
  • B. The MRP list has the status "processed".
  • C. The stock/requirements list displays the production order.
  • D. The stock/requirements list was updated the moment it was accessed.

Answer: C,D

 

NEW QUESTION 35
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default.
However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?

  • A. Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
  • B. Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.
  • C. Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
  • D. Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.

Answer: B

 

NEW QUESTION 36
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

  • A. In-house production time (material master)
  • B. Formulas (work center)
  • C. Standard values (routing)
  • D. Operation control key (routing)
  • E. Transport time (routing)

Answer: B,C,D

 

NEW QUESTION 37
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?

  • A. 8 hours
  • B. 5.6 hours
  • C. 7 hours
  • D. 6.16 hours

Answer: B

 

NEW QUESTION 38
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling? (Choose three)

  • A. Standard values in the operations of routings
  • B. General operation values of routings
  • C. User-defined fields in the operation of routings
  • D. General item values of bill of materials
  • E. General values from work scheduling view of the material master

Answer: A,B,C

 

NEW QUESTION 39
Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)

  • A. The planning of MPS and non-MPS items is always carried out in one planning run.
  • B. MPS items can be defined on plant level.
  • C. MPS items can be defined on MRP area level.
  • D. Non-MPS items can be taken into consideration by an MPS run.
  • E. MPS items are planned in a standard MRP run.

Answer: B,C,D

 

NEW QUESTION 40
Which functions can be triggered before releasing a production order? (Choose three)

  • A. Confirmation
  • B. Selection of a BOM
  • C. Selection of a routing
  • D. Stock determination
  • E. Scheduling

Answer: B,C,E

 

NEW QUESTION 41
Which data forms the basis for calculating the capacity requirement for an operation?
(Choose three.)

  • A. In-house production time (material master)
  • B. Formulas (work center)
  • C. Standard values (routing)
  • D. Operation control key (routing)
  • E. Transport time (routing)

Answer: B,C,D

 

NEW QUESTION 42
Which of the following statements best defines SAP ERP?

  • A. SAP ERP is an application that supports all processes involving direct customer contact throughout the entire customer relationship life cycle.
  • B. SAP ERP is a system hardware that includes components such as Purchasing, Sales and Distribution, Materials Management, and Production.
  • C. SAP ERP is a system in which advanced planning and optimization processes can be mapped.
  • D. SAP ERP is an application that a company can use to manage its business processes efficiently.

Answer: D

 

NEW QUESTION 43
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?

  • A. Planning with make-to-stock (strategy 10)
  • B. Planning at the assembly level (strategy 70)
  • C. Planning with final assembly (strategy 40)
  • D. Planning without final assembly (strategy 50)

Answer: D

 

NEW QUESTION 44
In which scenario will the error message shown in the attached screenshot occur?
Exhibit:

Exhibit

  • A. The selection method is set to "selection only by production version" in the material master.
  • B. A valid routing exists, but the material master is set to manual routing selection.
  • C. A valid routing exists, but the Customizing for the order type is set to manual routing selection.
  • D. The routing is not valid at the explosion date.

Answer: D

 

NEW QUESTION 45
Which of the following statements about the SAP Solution Manager listed is correct?

  • A. Solution Manager is a stand-alone system that communicates with other systems in a system landscape.
  • B. Solution Manager is an add-on industry solution.
  • C. Solution Manager is part of the SAP ECC System.
  • D. Solution Manager is a satellite system in a system landscape.

Answer: A

 

NEW QUESTION 46
What can you use to organize material staging for production orders? (Choose three)

  • A. Material documents
  • B. Transfer orders
  • C. Logistics Information System (LIS)
  • D. Pull list
  • E. KANBAN

Answer: B,D,E

 

NEW QUESTION 47
Which of the following functions does SAP Supply Chain Management (SCM) offer?

  • A. Product development, safety, quality, and maintenance
  • B. Communication with customers through different interaction channels
  • C. Planning of supply chains across company boundaries
  • D. Optimization of the procurement strategy with the supplier pool

Answer: C

 

NEW QUESTION 48
What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)

  • A. Reservations are no longer relevant for material requirements planning.
  • B. The order is no longer relevant for material requirements planning.
  • C. The order and its operations receive the system status Locked (LKD).
  • D. Capacity requirements are set to null.
  • E. Confirmations are no longer possible.

Answer: A,B,D

 

NEW QUESTION 49
......