100% Guaranteed Results 010-151 Unlimited 138 Questions [2022]
010-151 Dumps PDF - Want To Pass 010-151 Fast
More about the Exam
In 010-151 exam, 65-75 questions will appear. The applicants need to be ready to tackle MCQs, testlets, drag-and-drops, and items of other types. Regarding time, there will be 90 minutes to explore and complete the test. The only available language for 010-151 is English.
NEW QUESTION 12
Refer to the exhibit.
This image shows a CPU Pick-and-Place tool and a CPU Socket Protective Cap Removal tool.
Which types of Cisco UCS servers and Intel Xeon processors do these tools support?
- A. Cisco UCS B200 M3 Blade Server, B420 M3 Blade Server, C220 Rack Server, C240 Rack Sever, and C420 Rack Sever with Intel Xeon E5-2600 Series processors
- B. Cisco UCS B200 M3 Blade Server, B420 M3 Blade Server, C220 Rack Server, C240 Rack Sever, and C420 Rack Sever with Intel Xeon E5-2400 Series processors
- C. Cisco UCS B22 Blade Server, C22 Rack Server, and C24 Rack Sever with Intel Xeon E5-2600 Series processors
- D. Cisco UCS B22 Blade Server, C22 Rack Server, and C24 Rack Sever with Intel Xeon E5-2400 Series processors
Answer: A
NEW QUESTION 13
Refer to the exhibit.
Where is the best place to see bootflash free space?
- A. A - Available Memory
- B. B - Total Memory
- C. D - High Availability Details
- D. C - Local Storage Information
Answer: D
NEW QUESTION 14
Which two statements about Cisco UCS S3260 Storage Server are true? (Choose two.)
- A. Massive 840-TB data storage capacity
- B. It is in a compact 2-RU form factor.
- C. Up to 1 TB of Intel Optane DC Persistent Memory
- D. Support for the Cisco 12-G 9460-8i PCIe SAS RAID controller
- E. AMD EPYC 7000 series processors, with up to 32 cores per socket
Answer: A,D
Explanation:
Explanation/Reference: https://www.cisco.com/c/dam/en/us/products/collateral/servers-unified-computing/ucs-s-series- storage-servers/s3260-specsheet.pdf
NEW QUESTION 15
Refer to the exhibit.
What does it mean when item 7 (System Status LED) has a blinking red status?
- A. Power on Self-Test (POST) failed
- B. Major fault with memory DIMM
- C. Major fault with the system board
- D. Secure boot validation has failed
- E. Power shut down by software
Answer: A
NEW QUESTION 16
Which two statements about DIMM replacement in Cisco UCS Servers are true? (Choose two.)
- A. If the memory in a server is not fully populated, you can install DIMMs in any open slot.
- B. In servers that require pairs of DIMMs, the pairs must be identical (manufacturer, size, part #, and so on).
- C. Rack-mount and blade servers have memory fault LEDs that indicate which DIMM requires attention.
- D. In blade servers, DIMMs can be installed in either 1, 2, 4, or 8 DIMMs per channel.
Answer: B,D
NEW QUESTION 17
What is Platform as a Service?
- A. It configures, manages and develops networking environment for your application.
- B. It is the software development framework and components delivered over the network on a pay-as-you-go basis.
- C. It is where servers and virtual machines (VMs), network and storage are delivered over the network on a pay-as-you-go basis.
- D. It is when an application service is delivered over the network on a subscription basis.
Answer: B
NEW QUESTION 18
Which two statements about FCoE are true? (Choose two.)
- A. It allows Ethernet traffic to run over a Fibre Channel infrastructure.
- B. Encapsulates Ethernet frames into Fibre Channel frames, which allows them to run alongside traditional IP traffic.
- C. Allows Fibre Channel and Ethernet networks to share a single, integrated infrastructure.
- D. Consolidates I/O traffic in the data center.
- E. Increases capital costs due to the difficulty to manage.
Answer: C,D
NEW QUESTION 19
On which three devices can the Host Upgrade Utility be performed? (Choose three.)
- A. B230
- B. B460
- C. C210
- D. C420
- E. C230
- F. C240
- G. B210
Answer: C,D,F
NEW QUESTION 20
When replacing a standalone C-Series server which order will be used to shut down the server via CIMC?
- A. Click Host power, Click Shut off
- B. Click Power off, Click Shut down
- C. Click Power off, Click Shut off
- D. Click Host power, Click Shut down
Answer: B
NEW QUESTION 21
Which supervisor module is supported by a Cisco Nexus 7700 Series Switch?
- A. second-generation supervisor enhanced module (Sup2E)
- B. first-generation supervisor module
- C. third-generation supervisor enhanced module (Sup3E)
- D. second-generation supervisor module (Sup2)
Answer: A
NEW QUESTION 22
Which two virtualization technologies are used in a modern data center design? (Choose two.)
- A. Application virtualization
- B. Server virtualization
- C. Cloud virtualization
- D. Platform virtualization
- E. Storage virtualization
Answer: B,D
NEW QUESTION 23
With which data center type can a company lease the equipment and infrastructure?
- A. Managed services data center
- B. Enterprise data center
- C. Green technology data center
- D. Colocation data center
Answer: A
NEW QUESTION 24
How many 10GBASE-T port licenses are preinstalled on a Cisco Nexus 3064-32T?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
NEW QUESTION 25
A company wants to build a data center infrastructure which can provide up to 99.982% uptime availability per year. Which ANSI/TIA-942 data center tier meets the requirement?
- A. Concurrently maintainable site infrastructure
- B. Redundant-distribution site infrastructure
- C. Basic site infrastructure
- D. Redundant-capacity component site infrastructure
Answer: A
Explanation:
Explanation/Reference: https://www.doc.ic.ac.uk/~jgiceva/teaching/ssc18-cloud.pdf page 16
NEW QUESTION 26
Which five things should the administrator verify after performing maintenance or replacing a blade server? (Choose five.)
- A. hard drive status
- B. mezzanine card status
- C. host OS boot status
- D. CPU status
- E. blade server status
- F. fan and power status
- G. memory DIMM status
Answer: A,B,D,E,G
NEW QUESTION 27
Which statement is true about cloud computing?
- A. Users usually own and maintain their own IT infrastructure and facility.
- B. It increases total cost of ownership.
- C. It provides self-service, on-demand provisioning and a billing for corporate usage only.
- D. It provides end-to-end server, application network service, and storage virtualization.
Answer: D
NEW QUESTION 28
When activating the firmware via UCSM which two firmware versions must be activated at the same time?
- A. System and Kernel
- B. UCS Manger and Kernel
- C. UCS Manager and System
- D. CIMC and Kernel
Answer: A
NEW QUESTION 29
Which type of optics module is supported by a 12-port 100 GE Cisco Nexus 7700 F3 Series I/O module?
- A. QSFP+
- B. SFP/SFP+
- C. CFP
- D. CPAK
Answer: D
NEW QUESTION 30
Which two remote file system methods are used in the training material to transfer firmware to the Fabric Interconnect? (Choose two.)
- A. FTP
- B. TFTP
- C. FTPS
- D. RSH
Answer: A,B
NEW QUESTION 31
Which three tools are necessary to console into a Cisco UCS C-Series Rack-Mount Server? (Choose three.)
- A. Cisco DB-9-to-RJ-45 console cable
- B. keyboard
- C. KVM dongle
- D. USB serial adapter
- E. laptop
- F. monitor
Answer: B,C,F
Explanation:
Explanation/Reference:
answer is well modified.
NEW QUESTION 32
Which two firmware components does the Host Upgrade Utility upgrade? (Choose two.)
- A. System BIOS
- B. Fabric Interconnect firmware
- C. CIMC
- D. Cisco UCS Infrastructure software
- E. Cisco UCS Manager
Answer: A,C
Explanation:
Explanation/Reference: https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/c/sw/lomug/2-0-x/3_0/b_huu_3_0_1/ b_huu_2_0_13_chapter_011.html
NEW QUESTION 33
Refer to the exhibit.
Where is the best place to see whether the system is ready for a Fabric Interconnect failover?
- A. E - High Availability Details
- B. D - Access
- C. C - Part Details
- D. A - Overall Status operable
- E. B - L1 Connection
Answer: A
NEW QUESTION 34
A company wants to build a data center infrastructure which can provide up to 99.982% uptime availability per year. Which ANSI/TIA-942 data center tier meets the requirement?
- A. Concurrently maintainable site infrastructure
- B. Redundant-distribution site infrastructure
- C. Basic site infrastructure
- D. Redundant-capacity component site infrastructure
Answer: A
NEW QUESTION 35
......
Updated Verified 010-151 Q&As - Pass Guarantee: https://www.real4prep.com/010-151-exam.html
010-151 Practice Exam Dumps - 99% Marks In Cisco Exam: https://drive.google.com/open?id=1pl8pA69i87KNKtPcEUVIG9dT1XftXDgo