NEW QUESTION # 49
Which inspection origin creates only unplanned physical samples?

  • A. 2 goods issue
  • B. 15 sample management
  • C. 16 stability study
  • D. 3 production

Answer: B


NEW QUESTION # 50
What master data can you integrate into a task list for a production order?

  • A. Classification
  • B. Control Indicator
  • C. MIC
  • D. Material Specifications

Answer: C


NEW QUESTION # 51
To use an inspection plan without multiple specification , you must assign a material master and plant. What additional data can you assign to an inspection plan?(2 correct Ans)

  • A. Vendor
  • B. Inspection type
  • C. Notification type
  • D. Search field
  • E. Customer

Answer: A,E


NEW QUESTION # 52
A buyer wants to quality management department to approve a new vender malarial
-combination.
After activating the QM in procurement process , what the quality management department ensure in......
Correct 2

  • A. The inspection plan includes a relevant control key at operation level
  • B. The material master has an active inspection type
  • C. The material master has a relevant QM Control key assigned to it
  • D. A valid release quality info record exists
  • E. A quality agreement for vendor master exists

Answer: D,E


NEW QUESTION # 53
Your customer wants to automatically valuate the overall results of an audit using the standard Which valuation method book scores for the overall result?(2 Correct ans )

  • A. Quantitative valuation
  • B. Qualitative valuation
  • C. Valuation mode
  • D. Non relevant indicator

Answer: A,B


NEW QUESTION # 54
You have determined a new business inspection process and need to customize a new inspection type Which of the following activities must you complete? Correct 2

  • A. Assign Task list type to material types
  • B. Define goods movement type
  • C. Assign inspection type to inspection lot origin
  • D. Define default values for inspection type

Answer: C,D


NEW QUESTION # 55
Your customer wants material -dependent code selected from a catalog to show when a Where can you control and limit the codes?

  • A. Product hierarchy
  • B. Catalog settings
  • C. Catalog profile
  • D. Catalog groups

Answer: C


NEW QUESTION # 56
The IMG includes a customizing activity in which you assign object categories to a notification type? Which of the following object category already exist in standard setting? (3 Correct Ans)

  • A. Purchase order item
  • B. V Material
  • C. Order(pp-pi)
  • D. \/ Serial Number
  • E. V Batch

Answer: B,D,E


NEW QUESTION # 57
Which QM master data must you maintain to separate a sample into a primary and reserve sample?

  • A. Sample drawing procedure
  • B. Sample size
  • C. Sample determination
  • D. Sample processes

Answer: A


NEW QUESTION # 58
After you create customer master records, you define second inspection related default specification in the ....
Which of the followings options can you use to control when the quality inspection take place (2 correct ans)

  • A. The inspection occurs after the release of the sales order
  • B. The inspection occurs after the transport order is quit.
  • C. The inspection occurs after the good issue in posted
  • D. The inspection occurs before the good issue in posted

Answer: C,D


NEW QUESTION # 59
Which object must combined in test scheduling in the stability study Correct 3

  • A. Physical samples
  • B. Strategy
  • C. Physical drawing procedure
  • D. Initial sample
  • E. Inspection plans

Answer: A,B,E


NEW QUESTION # 60
You define a priority type in the implementation guide (img) and assign it to a notification type. When you enter a priority during creation of notification, what can the system do?

  • A. Send one or more e-mails to involved partners
  • B. Calculate the notification start and finish dates.
  • C. Start workflow to inform the responsible person(s)
  • D. Create one or more task automatically

Answer: B


NEW QUESTION # 61
Your customer requires the lab to use quantitate characteristics during a production result recording.
Which result confirmation control indicators are available for quantitative results

  • A. Summarized
  • B. Class confirmation
  • C. Mean value
  • D. Tolerance keys
  • E. Single value

Answer: A,B,E


NEW QUESTION # 62
From which tables does quality management information system (QMIS) retrieve data?

  • A. Structure figures
  • B. Control charts
  • C. Info structure
  • D. Early warning processes

Answer: C


NEW QUESTION # 63
Which type of inspection point exist in the system.(3 correct ans)

  • A. Inspection point for incoming certificates
  • B. Inspection point for functional location
  • C. Inspection point for Physical sample
  • D. Inspection point for equipment
  • E. Inspection point for defects recording

Answer: B,C,D


NEW QUESTION # 64
During an in process inspection for production orders, such as inspection type 09, which inventory posting is possible?

  • A. Quality stock
  • B. Unrestricted Stock
  • C. Blocked stock
  • D. None

Answer: D


NEW QUESTION # 65
Your consumer wants to perform an inspection at the vender's site instead of performing one during goods receipt.....
Where must you change the settings in the system?

  • A. Quality info record in procurement
  • B. Vendor master
  • C. Purchase order
  • D. Material master

Answer: A


NEW QUESTION # 66
Which of the following documents can you use as a reference document when creation a customer claim?(2 correct ans )

  • A. Delivery
  • B. QM order
  • C. Sales order
  • D. Material document
  • E. Quotation

Answer: A,C


NEW QUESTION # 67
Which following inspection origin are directly related to sale and distribution (SD) functions 3 correct answers

  • A. Plant maintenance
  • B. Good receipts
  • C. Delivery to customer with customer order
  • D. General delivery
  • E. Goods issue

Answer: B,C,D


NEW QUESTION # 68
Your customer wants to periodically calibrate the quality management test equipment used in an inspection plan .
Which type of test equipment must used ?

  • A. Production resource/ tools PRTs
  • B. Equipment
  • C. Materials
  • D. Documents

Answer: B


NEW QUESTION # 69
Your customer wants to add the quality score of a material as criterion for the vendor evaluation Where do you set the calculation procedure for the quality score:?

  • A. Quality info record in procurement
  • B. Vendor master
  • C. Material master
  • D. Dud code

Answer: D


NEW QUESTION # 70
For which structure elements of a quality notification can you assign a status profile? Note : 2 correct answer

  • A. Items
  • B. Tasks
  • C. Follow up actions
  • D. Header
  • E. Activities

Answer: B,D


NEW QUESTION # 71
Which settings are required for the immediate creation of inspection instruction during goods receipt process. Note : 3 correct answer

  • A. Inspection type settings in the implementation guide (IMG)
  • B. Inspection type settings in Material master
  • C. Settings for print control in implementation Guide (IMG)
  • D. Control setting in characteristic of the task list
  • E. Control setting in quality info record

Answer: A,C,D


NEW QUESTION # 72
Your customer plan to use Test Equipment Management as part of QM.
What event triggers the creation of an inspection lot for calibration inspection?

  • A. Release of a maintenance order
  • B. Assignment of Equipment to a maintenance plan
  • C. Creation of maintenance order
  • D. Scheduling a maintenance plan

Answer: A


NEW QUESTION # 73
your consumer want the section of a usage decision code to automatically trigger a goods movement . Where do you make the settings to enable this ?

  • A. in the movement type
  • B. in the code groups and code
  • C. in the selected set .
  • D. in the inspection type

Answer: C


NEW QUESTION # 74
......